1

Select the developer-specific requirement ?

A Portability
B Maintainability
C Availability
D Both Portability and Maintainability
Correct Answer D
2

Which one of the following is not a step of requirement engineering?

A elicitation
B design
C analysis
D documentation
Correct Answer B
3

Which of the following property does not correspond to a good Software Requirements Specification (SRS) ?

A Verifiable
B Ambiguous
C Complete
D Traceable
Correct Answer B
4

Which of the following property of SRS is depicted by the statement : β€œConformity to a standard is maintained” ?

A Correct
B Complete
C Consistent
D Modifiable
Correct Answer B
5

Which of the following statements about SRS is/are true? i) SRS is written by customer. ii) SRS is written by a developer. iii) SRS serves as a contract Between customer and developer

A Only i is true
B Both ii and iii are true
C All are true
D None of the mentioned
Correct Answer C
6

Which of the following is included in SRS ?

A Cost
B Design Constraints
C Staffing
D Delivery Schedule
Correct Answer B
7

Consider the following Statement: β€œThe data set will contain an end of file character.”What characteristic of SRS is being depicted here ?

A Consistent
B Non-verifiable
C Correct
D Ambiguous
Correct Answer B
8

Consider the following Statement: β€œThe product should have a good human interface.”What characteristic of SRS is being depicted here ?

A Consistent
B Non-Verifiable
C Correct
D Ambiguous
Correct Answer B
9

Consider the following Statement: β€œThe output of a program shall be given within 10 secs of event X 10% of the time.”What characteristic of SRS is being depicted here ?

A Consistent
B Verifiable
C Non-verifiable
D Correct
Correct Answer B
10

Why is Requirements Management Important ? It is due to the changes

A to the environment
B in technology
C in customer’s expectations
D in all of the mentione
Correct Answer D
11

Which of the following is a requirement management activity ?

A Investigation
B Design
C Construction and Test
D All of the mentioned
Correct Answer D
12

Which one of the following is a functional requirement ?

A Maintainability
B Portability
C Robustness
D None of the mentioned
Correct Answer D
13

Which one of the following is a requirement that fits in a developer’s module ?

A Availability
B Testability
C Usability
D Flexibility
Correct Answer B
14

"Consider a system where, a heat sensor detects an intrusion and alerts the security company." What kind of a requirement the system is providing ?

A Functional
B Non-Functional
C Known Requirement
D None of the mentioned
Correct Answer A
15

Which of the following is not a non-functional requirement?

A Portability
B Security
C Scalibility
D User Intereaction
Correct Answer D
16

The process to gather the software requirements from client, analyze and document them is known as ___________________.

A Feasibility Study
B Requirement Gathering
C Requirement Engineering
D System Requirements Specification
Correct Answer C
17

The goal of requirement engineering is to develop and maintain sophisticated and descriptive _________________ document.

A Feasibility Study
B Requirement Gathering
C Software Requirement Validation
D System Requirements Specification
Correct Answer D
18

It is the process in which developers discuss with the client and end users and know their expectations from the software.

A Requirements gathering
B Organizing Requirements
C Negotiation & discussion
D Documentation
Correct Answer A
19

The result of the requirements engineering task is an analysis model that defines which of the following problem domain(s)?

A Information
B Functional
C Behavioral
D All of the above
Correct Answer D
20

Which one of the following is a functional requirements?

A Maintainability
B Portability
C Business Need
D Reliability
Correct Answer C
21

Good Characteristics of SRD

A Unambiguousness
B Verifiability
C Testability
D All of the above
Correct Answer D
22

The Document produced at the end of the requirements phase of software development cycle is known as______________

A SRS/SRD
B URD
C SRU
D None
Correct Answer A
23

Require elicitation is the process of _________ actual requirements.

A Gathering
B Splitting
C Reviews
D None of the above
Correct Answer A

True / False & Short Questions

24 System Requirement is written for_____________(User / Developer)
Correct Answer Developer
25 Requirements elicitation is a cyclic process(True / False)?
Correct Answer True
26 Narrative essay is one of the best types of specification document?(True / False)
Correct Answer False
27 Requirements Management is a prerequisite for Quality-Oriented Development.(True / False)
Correct Answer True
28 It is relatively common for different customers to propose conflicting requirements, each arguing that his or her version is the right one.( True/ False)
Correct Answer True
29 The job of the requirements engineer is to categorize all stakeholder information in a way that allows decision makers to choose an internally consistent set of requirements.(True / False)
Correct Answer True
30 Non-functional requirements can be safely ignored in modern software development projects.( True / False)
Correct Answer False