☑ MCQ PRACTICE

Software Process & Project Management Unit 3

Practice objective questions for quick revision and examination preparation. Try answering each question before revealing the answer.

📚 Software Process & Project Management
📖 Unit 3
🎯 MCQs
Software Process & Project Management MCQs - Unit 3

Software Process & Project Management MCQs - Unit 3

1

The number of core workflows in the software process is

A three
B five
C nine
D seven
Correct Answer seven
2

Which of the following is NOT a core workflow of the software process?

A Management
B Requirements
C Billing
D Assessment
Correct Answer Billing
3

The workflow that deals with planning, risk management and project control is the

A design workflow
B management workflow
C assessment workflow
D deployment workflow
Correct Answer management workflow
4

The environment workflow mainly deals with

A writing source code only
B negotiating contracts
C training end users
D automating the process and the development environment
Correct Answer automating the process and the development environment
5

The assessment workflow includes

A marketing and sales
B payroll processing
C hardware installation
D testing and reviews
Correct Answer testing and reviews
6

In the inception phase, the iteration emphasis is on

A implementation
B deployment
C assessment only
D management and requirements
Correct Answer management and requirements
7

In the elaboration phase, the iteration emphasis is on

A deployment
B marketing
C maintenance
D design (architecture)
Correct Answer design (architecture)
8

In the construction phase, the iteration emphasis is on

A implementation
B requirements
C management only
D business case
Correct Answer implementation
9

In the transition phase, the iteration emphasis is on

A design
B business case
C assessment and deployment
D requirements
Correct Answer assessment and deployment
10

The number of major milestones in the software process is

A four
B two
C three
D six
Correct Answer four
11

Major milestones are held at the end of each

A workflow
B week
C method
D life-cycle phase
Correct Answer life-cycle phase
12

Which of the following is a minor milestone?

A Life-Cycle Objective
B Life-Cycle Architecture
C Product Release Milestone
D Iteration readiness review
Correct Answer Iteration readiness review
13

Periodic status assessments are used to

A keep stakeholders informed about progress, quality and risk
B replace all milestones
C write source code
D test the hardware
Correct Answer keep stakeholders informed about progress, quality and risk
14

WBS stands for

A Work Budget System
B Web Based Software
C Work Breakdown Structure
D Weekly Budget Summary
Correct Answer Work Breakdown Structure
15

A conventional WBS is organised around

A the process workflows
B the customer's budget
C the software product (its components)
D the team members' names
Correct Answer the software product (its components)
16

An evolutionary WBS is organised around

A the process workflows and phases
B the product directory structure
C the programming languages
D the hardware
Correct Answer the process workflows and phases
17

In a typical effort distribution, the elaboration phase takes about

A 5%
B 20%
C 65%
D 10%
Correct Answer 20%
18

In a typical effort distribution, the construction phase takes about

A 65%
B 5%
C 20%
D 10%
Correct Answer 65%
19

In a typical effort distribution, the inception phase takes about

A 20%
B 65%
C 5%
D 30%
Correct Answer 5%
20

In a typical schedule distribution, the construction phase takes about

A 10%
B 50%
C 30%
D 90%
Correct Answer 50%
21

An estimate built by adding up the costs of individual WBS elements is called

A bottom-up estimation
B top-down estimation
C random estimation
D analogy only
Correct Answer bottom-up estimation
22

An estimate that starts from the overall project cost and divides it among the parts is

A bottom-up estimation
B top-down estimation
C item-by-item estimation
D unit costing
Correct Answer top-down estimation
23

An iteration plan describes

A the retirement of the product
B the marketing strategy
C the hardware purchase
D what is to be accomplished in a particular iteration
Correct Answer what is to be accomplished in a particular iteration
24

Iterations in the elaboration phase are mainly planned according to

A profit
B colour of the user interface
C risk
D employee seniority
Correct Answer risk
25

In iterative development, project plans are

A refined continuously as more is learned
B written once and never changed
C discarded after the first week
D kept secret from the team
Correct Answer refined continuously as more is learned

Fill in the Blanks

26 The seven core workflows are management, environment, requirements, design, implementation, assessment and ______.
Correct Answer deployment
27 The four major milestones are LCO, LCA, IOC and ______.
Correct Answer PRM (Product Release Milestone)
28 WBS stands for ______.
Correct Answer Work Breakdown Structure
29 A conventional WBS is organised around the software ______.
Correct Answer product
30 An evolutionary WBS is organised around the ______ workflows.
Correct Answer process
31 In a typical effort distribution, inception takes 5%, elaboration takes ______, construction takes 65% and transition takes 10%.
Correct Answer 20%
32 In a typical schedule distribution, the elaboration phase takes about ______.
Correct Answer 30%
33 In a typical schedule distribution, the inception phase takes about ______.
Correct Answer 10%
34 Minor milestones include the iteration ______ review and the iteration assessment review.
Correct Answer readiness
35 The ______ workflow includes testing and reviews.
Correct Answer assessment
36 The environment workflow deals with automating the ______.
Correct Answer process
37 In the elaboration phase, the main workflow emphasis is on ______.
Correct Answer design
38 Estimating by adding up the costs of individual WBS elements is called ______ estimation.
Correct Answer bottom-up
39 Iterations in the elaboration phase are planned mainly according to ______.
Correct Answer risk
40 Periodic status assessments help track progress, quality and ______.
Correct Answer risk
← Back to All MCQs