Software Process & Project Management MCQs - Unit 5

Software Process & Project Management MCQs - Unit 5

1

CCPDS-R stands for

A Central Computer Planning and Data System – Revised
B Common Code Processing and Debug System – Release
C Command Control Planning and Design Software – Rework
D Command Center Processing and Display System – Replacement
Correct Answer Command Center Processing and Display System – Replacement
2

The CCPDS-R case study project was developed by

A Microsoft
B Oracle
C Infosys
D TRW
Correct Answer TRW
3

The programming language used in the CCPDS-R project was

A C++
B Java
C Python
D Ada
Correct Answer Ada
4

The CCPDS-R project followed which kind of approach?

A Pure waterfall approach
B Code-and-fix approach
C Iterative, architecture-first approach
D Ad hoc approach
Correct Answer Iterative, architecture-first approach
5

The first principle of modern software management is to base the process on

A a code-first approach
B a marketing-first approach
C an architecture-first approach
D a hardware-first approach
Correct Answer an architecture-first approach
6

The second principle of modern software management is to establish an iterative life-cycle process that

A postpones risk to the end
B confronts risk early
C ignores risk
D avoids all testing
Correct Answer confronts risk early
7

The third principle of modern software management is to transition design methods to emphasise

A monolithic development
B hand-coded assembly
C paper-based design
D component-based development
Correct Answer component-based development
8

The sixth principle is to capture design artifacts in

A rigorous, model-based notation
B free-form text only
C spoken conversations
D handwritten notes only
Correct Answer rigorous, model-based notation
9

The seventh principle is to instrument the process for objective quality control and

A marketing analysis
B salary calculation
C progress assessment
D customer entertainment
Correct Answer progress assessment
10

The eighth principle is to use which approach to assess intermediate artifacts?

A Opinion-based approach
B Paper-based approach
C Demonstration-based approach
D Guess-based approach
Correct Answer Demonstration-based approach
11

The fourth principle is to establish a

A marketing environment
B change management environment
C hardware laboratory
D voting system
Correct Answer change management environment
12

The tenth principle is to establish a configurable process that is economically

A scalable
B fixed
C secret
D expensive
Correct Answer scalable
13

Tools that support round-trip engineering enhance

A change freedom
B only printing speed
C hardware cost
D network bandwidth
Correct Answer change freedom
14

In a modern process, risks are resolved

A only after delivery
B only in the final week
C early in the life cycle
D never
Correct Answer early in the life cycle
15

In modern iterative projects, integration takes place

A continuously throughout the life cycle
B only once at the very end
C never
D only after release
Correct Answer continuously throughout the life cycle
16

In a modern process, early demonstrations help to

A hide design flaws
B delay testing
C expose design flaws early
D avoid customer feedback
Correct Answer expose design flaws early
17

In a modern process, good and bad project performance becomes apparent

A only after delivery
B only after maintenance
C never
D much earlier in the life cycle
Correct Answer much earlier in the life cycle
18

Transition to a modern process requires mainly a

A cultural shift in management and team attitudes
B change of office furniture
C change of company logo
D change of programming font
Correct Answer cultural shift in management and team attitudes
19

In a modern process, requirements and design are

A frozen at the start
B never documented
C fluid and evolve through iterations
D decided by the customer alone
Correct Answer fluid and evolve through iterations
20

Next-generation software economics aims to improve productivity mainly through

A longer working hours
B reuse, component-based development and automation
C bigger teams only
D more paper documentation
Correct Answer reuse, component-based development and automation
21

COCOMO is a

A software cost estimation model
B programming language
C database system
D network protocol
Correct Answer software cost estimation model
22

COTS stands for

A Custom Online Testing System
B Common Object Tracking Service
C Commercial Off-The-Shelf
D Controlled Open Test Software
Correct Answer Commercial Off-The-Shelf
23

Reusing COTS components helps to

A reduce the size of the software to be developed
B increase the number of lines to be written
C avoid all integration
D remove the need for architecture
Correct Answer reduce the size of the software to be developed
24

A modern project profile emphasises early and continuous

A isolation
B deletion
C printing
D integration
Correct Answer integration
25

Which of the following is a modern project profile practice?

A Freezing all requirements before design
B Evolutionary requirements with teamwork among stakeholders
C Keeping the customer away from the project
D Postponing integration until the end
Correct Answer Evolutionary requirements with teamwork among stakeholders

Fill in the Blanks

26 CCPDS-R stands for Command Center Processing and Display System – ______.
Correct Answer Replacement
27 The CCPDS-R project was developed by ______.
Correct Answer TRW
28 The programming language used in the CCPDS-R project was ______.
Correct Answer Ada
29 The first principle of modern software management is to base the process on an ______-first approach.
Correct Answer architecture
30 The second principle is to establish an iterative life-cycle process that confronts ______ early.
Correct Answer risk
31 The third principle is to transition design methods to emphasise ______-based development.
Correct Answer component
32 The sixth principle is to capture design artifacts in rigorous ______-based notation.
Correct Answer model
33 The eighth principle is to use a ______-based approach to assess intermediate artifacts.
Correct Answer demonstration
34 The seventh principle is to instrument the process for objective quality control and ______ assessment.
Correct Answer progress
35 Tools that support round-trip engineering enhance change ______.
Correct Answer freedom
36 COCOMO stands for ______.
Correct Answer Constructive Cost Model
37 In a modern process, early demonstrations expose design ______ early.
Correct Answer flaws
38 Transition to a modern process requires a ______ shift in management and team attitudes.
Correct Answer cultural
39 COTS stands for Commercial ______-The-Shelf.
Correct Answer Off
40 The tenth principle is to establish a configurable process that is economically ______.
Correct Answer scalable